Vedanta South Africa zinc capacity doubles at Gamsberg

On 16 October 2026, President Cyril Ramaphosa and Vedanta director Priya Agarwal-Hebbar inaugurated the Gamsberg Phase II project. The ceremony marked one of the largest mining investments in the Northern Cape in recent years.
The expansion cost nearly US$600 million, according to company figures reported in October 2026. It doubles Gamsberg’s annual ore throughput from four million tonnes to eight million tonnes. Annual zinc-in-concentrate capacity now stands at approximately 500,000 tonnes, per South African government data for October 2026.
The investment forms part of a broader R21 billion commitment Vedanta announced at the 2018 South Africa Investment Conference. Phase II is the most visible delivery on that pledge to date.
A larger platform in the Northern Cape
Gamsberg is the flagship mine of Vedanta Zinc International. It sits near Aggeneys in the Northern Cape, a province actively seeking greater local processing and industrial activity.
Construction employed more than 1,500 workers. The new concentrator anchors a broader industrial footprint in a remote region with limited economic alternatives.
Ramaphosa used the inauguration to call for local zinc smelting capacity in the province, according to South African government reporting for October 2026. That call reflects a wider push to move beyond raw concentrate exports and capture more processing value onshore.
What does the Gamsberg expansion mean for investors?
By FurtherAfrica’s reading of the numbers, the table below shows how Gamsberg fits within Vedanta’s group zinc strategy, based on company and government figures for October 2026.
| Measure | Reported figure |
|---|---|
| Gamsberg annual ore capacity | ~8 million tonnes (South African government data, October 2026) |
| Gamsberg zinc-in-concentrate capacity | ~500,000 tonnes (South African government data, October 2026) |
| Vedanta group zinc target (India and South Africa) | 3 million tonnes annually (company figures, October 2026) |
Vedanta targets three million tonnes of annual zinc production across India and South Africa. That total combines two million tonnes from Hindustan Zinc and one million tonnes from Vedanta Zinc International’s broader international portfolio, per company information reported in October 2026.
Gamsberg Phase II makes South Africa a larger pillar of Vedanta’s three-million-tonne zinc plan.
Larger throughput supports demand for power, transport and engineering services. Those supply-chain effects extend well beyond the mine gate. However, the next value test is whether South Africa captures smelting activity, not just concentrate production.
The government’s push for local processing adds a policy dimension that could shape the project’s long-term returns. Progress on smelting investment, alongside the concentrator ramp-up rate, will determine whether Phase II delivers capacity alone or a broader Northern Cape industrial base.
Investors should watch the ramp-up pace, infrastructure reliability and any concrete steps towards a local zinc smelter in the Northern Cape.
Quick answers
Vedanta invested nearly US$600 million in the Gamsberg Phase II project, according to company figures reported in October 2026.
Gamsberg’s annual zinc-in-concentrate capacity now stands at approximately 500,000 tonnes, with annual ore throughput doubling to eight million tonnes.
Vedanta targets three million tonnes of annual zinc production in total: two million tonnes from Hindustan Zinc in India and one million tonnes from Vedanta Zinc International’s international portfolio, per company figures for October 2026.