Benguela gas field confirms 41M scf/d at Katambi-2

FurtherAfrica

Benguela gas field confirms 41M scf/d at Katambi-2

Oct 22, 2026

The Benguela gas field has moved a step closer to development after Sonangol’s Katambi-2 well in Block 24 recorded a stabilised flow rate of 41 million standard cubic feet of gas per day, giving Angola a credible new domestic energy option.

Sonangol completed a formation test at Katambi-2 in October 2026, confirming productive reservoirs in Angola’s offshore Benguela basin. The well also yielded 1,160 barrels per day of condensate. These results give Angola’s national oil company a technical foundation for the next phase of appraisal work.

Katambi-2 Formation Test Results

41 Stabilised gas flow rate (million scf/day)
Industry data, October 2026
1160 Condensate output (barrels/day)
Industry data, October 2026
331 Combined productive thickness (metres)
Industry data, October 2026

Source: Industry data, October 2026

The well crossed two productive intervals with a combined thickness of 331 metres. Average porosity ranged from 9% to 12%, according to October 2026 industry data. Katambi-2 was drilled close to the earlier Katambi-1 location.

What does the Katambi-2 result mean for investors?

The flow test confirms deliverability. However, it does not yet establish recoverable reserves or final project economics. Sonangol and Angola’s National Oil, Gas and Biofuels Agency must still assess well count, processing facilities and pipeline needs, along with funding requirements, before any investment decision is possible.

The discovery contains non-associated gas. Angola’s upstream sector has traditionally centred on crude oil. This find broadens the country’s production mix and adds a domestic gas supply option that could support power generation and industrial activity.

By FurtherAfrica’s reading of the numbers, domestic use is the most immediate investment case. Export sales would depend on surplus volumes and infrastructure capacity, as well as commercial terms that remain to be defined.

Katambi-2 stabilised flow-test and reservoir results, October 2026
Metric Result
Stabilised gas flow rate 41 million scf/day
Condensate output 1,160 barrels/day
Combined productive thickness 331 metres
Average porosity range 9%–12%

Broader context for Angola’s energy push

The Benguela field sits within Angola’s wider effort to expand downstream and industrial capacity. In October 2026, Angola invited Namibia to consider an equity stake in the Lobito refinery, as discussed at the Angola-Namibia Business Forum in Luanda. Regional energy cooperation adds context, though any link to Katambi-2 remains prospective at this stage.

Offshore development will also require coordination with coastal fishing communities. Sonangol has indicated that petroleum operations and fishing can coexist, provided companies protect marine resources. Environmental assessment and maritime planning will therefore run alongside technical appraisal.

Africa Oil & Gas Report noted that the Katambi-2 results give Sonangol a solid technical basis for future investment decisions. The critical next milestones are appraisal drilling and development design, followed by commercial agreements. Investors should track those closely as Sonangol works to anchor the project on domestic demand before any export proposition emerges.

Quick answers
What did the Katambi-2 well test show?

The Katambi-2 well in Block 24 recorded a stabilised gas flow rate of 41 million standard cubic feet per day and 1,160 barrels per day of condensate, with two productive intervals totalling 331 metres in combined thickness.

Who operates the Benguela gas field in Angola?

Sonangol, Angola’s national oil company, operates the Benguela basin discovery and is working with Angola’s National Oil, Gas and Biofuels Agency to advance appraisal and development planning.

What are the next steps before production can begin?

Sonangol must complete appraisal drilling, assess recoverable reserves, design development infrastructure and finalise commercial agreements before any final investment decision or production timeline can be confirmed.

The post Benguela gas field confirms 41M scf/d at Katambi-2 appeared first on FurtherAfrica.